RECOLLECTING THE MASTERFORMAT DIVISION SEQUENCE
The first operation is the foundations for the walls. Because foundations are typically made of concrete, Concrete is Division 03. After the foundations have been completed, masonry work for the walls can begin. Thus, Masonry is Division 04. After the walls are completed, steel roof joists can be placed. Thus, Division 05 is Metals . The installation of the wood roof deck follows that of the steel joists. Hence, Wood, Plastics, and Composites is Division 06.
After the roof deck is erected, it must be insulated and protected against weather. Therefore, Thermal and Moisture Protection is Division 07. Roofing and waterproofing (of basements) are part of this division, as are wall insulation and joint sealants. The next step is to protect the rest of the envelope; hence, Division 08 is Openings . All doors and windows are part of this division, regardless of whether they are made of steel, aluminum, or wood.
With the envelope protected, finish operations, such as those involving the interior dry-wall, flooring, and ceiling, can begin. Thus, Division 09 is Finishes . Division 10 is Special-
ties , which consists of several items that cannot be included in the previous divisions, such
as toilet partitions, lockers, storage shelving, and movable partitions.
Obviously, the building must now receive all the necessary office, kitchen, laboratory, or other equipment. Thus, Division 11 is Equipment . Division 12 is Furnishings , followed by Special Construction (Division 13) and Conveying Equipment (Division 14).
Before any construction operation can begin, there must be references to items that apply to all divisions, such as payment procedures, product-substitution procedures, contract-modification procedures, contractor’s temporary facilities, and regulatory requirements imposed by the city or any other authority having jurisdiction. This is Division 01, General Requirements . Division 00 ( Procurement and Contracting Requirements ) refers to the requirements for the procurement of bids from prospective contractors.