CONSTRUCTION PHASE

Once the general contractor has been selected and the contract awarded, the construction work begins, as described in the   contract documents  . The contract documents are virtually the same as the bidding documents, except that the contract documents are part of a signed legal contract between the owner and the contractor. They generally do not contain Division 00 of the MasterFormat.

In preparing the contract documents, the design team’s challenge is to efficiently produce the graphics and text that effectively communicate the design intent to the construction professionals and the related product suppliers and manufacturers so that they can do the following:

  •    Propose accurate and competitive bids
  •    Prepare detailed and descriptive submittals for approval
  •    Construct the building with a minimum number of questions, revisions, and changes
   
SHOP DRAWINGS

The construction drawings and the specifications should provide a fairly detailed delineation of the building. However, they do not describe it to the extent that fabricators can produce building components directly from them. Therefore, the fabricators generate their own drawings, referred to as   shop drawings , to provide the higher level of detail necessary to fabricate and assemble the components.

Shop drawings are not generic, consisting of manufacturers’ or suppliers’ catalogs, but  are specially prepared for the project by the manufacturer, fabricator, erector, or subcontractors. For example, an aluminum window manufacturer must produce shop drawings to show that the required windows conform with the construction drawings and the specifications. Similarly, precast concrete panels, stone cladding, structural steel frame, marble or  granite flooring, air-conditioning ducts, and other components require shop drawings  before they are fabricated and installed.

Before commencing fabrication, the fabricator submits the shop drawings to the general  contractor. The general contractor reviews them, marks them “approved,” if appropriate, and then submits them to the architect for review and approval. Subcontractors or   manufacturers cannot submit shop drawings directly to the architect.

The review of all shop drawings is coordinated through the architect, even though they may actually be reviewed in detail by the appropriate consultant. Thus, the shop drawings pertaining to  structural components are sent to the architect and then to the structural consultant for review and approval. The fabricator generally begins fabrication only after receiving the architect’s review of the shop drawings.

The review of shop drawings by the architect is limited to checking that the work indicated therein conforms with the overall design intent shown in the contract documents. Approval of shop drawings that are later discovered to deviate from the  contract documents does not absolve the general contractor of the responsibility to comply with the contract documents for quality of materials, workmanship, or the dimensions of the fabricated components,  Figure  1.9.


MOCK-UP SAMPLES

In addition to shop drawings, full-size mock-up samples of one or more critical elements of the building may be required in some projects. This is done to establish the quality of materials and workmanship by which the completed work will be judged. For example, it is not unusual for the architect to ask for a mock-up of a  typical area of the curtain wall of a high-rise building before the fabrication of the actual curtain wall is undertaken. Mock-up samples go through the same approval process as the shop drawings.

OTHER SUBMITTALS

In addition to shop drawings and any mock-up samples, some other submittals required from the contractor for the architect’s review are:

•   Product  material  samples 
•   Product  data 
•   Certifications
•   Calculations

DBB METHOD—INVITATIONAL BIDDING

Invitational bidding, also called   closed bidding , is another variation of the DBB method that is generally used for quasi-public and some private projects. In this method, the owner preselects general contractors who have demonstrated, based on their experience, resources, and financial standing, their qualifications to perform the work. The selected contractors are then invited to bid for the project, and the contractor with the lowest bid is then awarded the contract. The architect (as the owner’s representative) may be involved in the prescreening process.

DBB METHOD—COMPETITIVE SEALED PROPOSAL

This method is very similar to competitive sealed bidding and is commonly used for publicly funded projects. The difference between competitive sealed bidding and competitive sealed proposal methods is that the owner’s selection of the general contractor is not based on price alone but also on such other criteria as the contractor’s past experience, safety record, proposed personnel, project schedule, and so on. To ensure fairness, the advertisement and bidding documents must provide the details of the selection criteria, with relative weightings assigned to each criterion.  

DBB METHOD—COMPETITIVE SEALED BIDDING

On several publicly funded projects, the award of a construction contract to the general contractor is based on   competitive sealed bidding , also called   open bidding . This refers to the process by which qualified contractors are invited to bid on the project. The invitation is generally issued through advertisements in newspapers, trade publications, and other public media.

The advertisement for bids includes a description of the project, its location, where to obtain the bidding documents, the price of the bidding documents, the bid opening date and location, and other important information. The purpose of the advertisement is to notify and thereby attract a sufficient number of contractors to compete for the construction contract.

The general contractor’s bid for the project is based on the information provided in the bidding documents . The bidding documents are essentially the construction document set with such additional items as the instructions to bidders, requirements with respect to the  financial and technical status of bidders (see the information on surety bonds in the box  “Expand Your Knowledge”), and the contract agreement form that the successful bidder  will sign when the contract is awarded. Because these additional items are text items, they  are bound together as a project manual, Figure 1.8.

  FIGURE 1.8  The project manual in the bidding document set includes specifications and
  Division 00. After the general contractor has been selected, the project manual (in the contract
document set) generally excludes Division 00.




In the competitive sealed bidding method, the bidding documents are generally given only to contractors who are capable, by virtue of their experience, resources, and financial standing, to bid for the project. Therefore, the architect (as the owner’s representative) may prescreen the bidders with respect to their reputation and ability to undertake the project.


An exception to prescreening for the release of bidding documents involves projects funded by the federal, state, or local government, for which almost anyone can access the bidding documents. However, even in this kind of project, the number of contractors who can actually submit the bids is practically limited. This limitation is generally the result of the financial security required from the bidders, known as a   bid bond . The bidder must obtain a bid bond from a surety company in the amount specified in the bidding documents. This bond is issued based on the contractor’s experience, ability to perform the work, and financial resources required to fulfill the contractual obligations.

Whether or not the release of the bidding documents is restricted, the procedure stated earlier ensures that all the bidders are similarly qualified with respect to financial ability, experience, and technical expertise. Because all bidders receive the same information and are of the same standing, the competition is fair; therefore, the contract is generally awarded to the lowest qualified bidder.    

DESIGN-BID-BUILD PROJECT DELIVERY METHOD

In the design-bid-build method, the general contractor is selected through competition. The owner obtains multiple bids for the project from which the general contractor, who provides the “best value for money,” is selected. Within this overall approach, several  versions are available to suit the requirements of the project and the particular needs of  the owner. Collectively, these delivery versions are referred to as the   design bid-build  (DBB) method because in this version, the design, bid, and construction phases of a  project are sequential, and one phase does not begin until the previous phase has been  completed,  Figure 1.7 . Following are three commonly used versions of the DBB method  of delivery:

  •    DBB method—competitive sealed bidding (open bidding)
  •    DBB method—competitive sealed proposal
  •    DBB  method— invitational  bidding   (closed  bidding)  

  FIGURE 1.7  Sequence of operations in the design-bid-build (DBB) method of project delivery. Note that the owner’s approval is required before proceeding from one phase or stage to the next.

GENERAL CONTRACTOR AND PROJECT DELIVERY METHODS

Selecting the general contractor is a crucial part of a project. A number of selection methods exist. The method used in selecting the general contractor, its timing, and the contractor’s obligations under the contract distinguishes one project delivery method from the other. Some of the most commonly used delivery methods are:

•    Design-bid-build  method
•    Design-negotiate-build  method
•    Construction manager as agent method
•     Construction  manager  at  risk   method
•    Design-build  method
•    Integrated  project  delivery  method

The design-bid-build method is the oldest and most familiar method of project delivery. This method is covered first. Because the essential features of construction and postconstruction phases are almost identical in all delivery methods, a discussion of what is included in these two phases is presented next. Subsequently, other methods are discussed in terms of how they differ from the design-bid-build method. The table “Project Delivery Methods at a Glance” provides a synopsis of these methods.

GENERAL CONTRACTOR AND PROJECT DELIVERY METHODS

CONSTRUCTION-RELATED INFORMATION

The preconstruction phase generally begins after the construction drawings and specifications have been completed and culminates in the selection of the construction team. The construction of even a small building involves so many specialized skills and trades that the work cannot normally be undertaken by a single construction firm. Instead, the work is generally done by a team consisting of the   general contractor  and a number of specialty subcontractors .

Thus, a project may have roofing; window and curtain wall; plumbing; and heating, ventilation, and air-conditioning (HVAC) subcontractors, among others, in addition to the general contractor. The general contractor’s own work may be limited to certain components of the building (such as the structural components—load-bearing walls, reinforced concrete beams and columns, roof and floor slabs, etc.), with all the remaining work subcontracted.

In contemporary projects, however, the trend is toward the general contractors not performing any actual construction work but subcontracting the work entirely to various sub-contractors. Because the subcontractors are contracted by the general contractor, only the general contractor is responsible and liable to the owner.

In some cases, a subcontractor will, in turn, subcontract a portion of his or her work  to another subcontractor, referred to as a   second-tier subcontractor, Figure 1.6. In  that  case, the general contractor deals only with the subcontractor, not the second-tier subcontractor.

Whether the general contractor performs part of the construction work or subcontracts  the entire work, the key function of the general contractor is the overall management of  construction. This includes coordinating the work of all subcontractors, ensuring that the  work done by them is completed in accordance with the contract documents, and ensuring  the safety of all workers on the site. A general contractor with a good record of site safety  not only demonstrates respect for the workers but also improves the profit margin by lowering the cost of construction insurance.

  FIGURE 1.6  Members of the construction team and their interrelationships with each other and
the owner. A solid line in this illustration indicates a contractual relationship between parties. A
dashed line indicates a communication link, not a contract. The relationships shown here are not
absolute and may change with the nature of the project.

RECOLLECTING THE MASTERFORMAT DIVISION SEQUENCE

Architectural design typically involves Divisions 2 to 14 of the Facilities Construction Subgroup. Although the basis for sequencing the Divisions in this subgroup is far more complicated, the first few divisions (those that are used in virtually all buildings) may be deduced by visualizing the sequence of postearthwork operations required in constructing the simple building shown in  Figure 1.5. The building consists of load-bearing masonry walls, steel roof joists, and wood roof deck.

  FIGURE 1.5  A simple load-bearing masonry wall building with steel roof trusses and wood roof
deck used as an aid to recalling the sequence of the first few (architecturally important) divisions of
the MasterFormat.




The first operation is the foundations for the walls. Because foundations are typically made of concrete,   Concrete  is Division 03. After the foundations have been completed, masonry work for the walls can begin. Thus,   Masonry  is Division 04. After the walls are completed, steel roof joists can be placed. Thus, Division 05 is   Metals . The installation of the wood roof deck follows that of the steel joists. Hence,   Wood, Plastics, and Composites is Division 06.


After the roof deck is erected, it must be insulated and protected against weather. Therefore,   Thermal and Moisture Protection  is Division 07. Roofing and waterproofing (of basements) are part of this division, as are wall insulation and joint sealants. The next step is to protect the rest of the envelope; hence, Division 08 is   Openings . All doors and windows are part of this division, regardless of whether they are made of steel, aluminum, or wood.

With the envelope protected, finish operations, such as those involving the interior dry- wall, flooring, and ceiling, can begin. Thus, Division 09 is   Finishes . Division 10 is Specialties , which consists of several items that cannot be included in the previous divisions, such as toilet partitions, lockers, storage shelving, and movable partitions.

Obviously, the building must now receive all the necessary office, kitchen, laboratory, or other equipment. Thus, Division 11 is   Equipment . Division 12 is   Furnishings ,  followed  by Special Construction  (Division 13) and   Conveying Equipment   (Division  14).   

Before any construction operation can begin, there must be references to items that apply to all divisions, such as payment procedures, product-substitution procedures, contract-modification procedures, contractor’s temporary facilities, and regulatory requirements imposed by the city or any other authority having jurisdiction. This is Division 01, General Requirements  . Division 00 (  Procurement and Contracting  Requirements  ) refers to the requirements for the procurement of bids from prospective contractors.

RECOLLECTING THE MASTERFORMAT DIVISION SEQUENCE

Architectural design typically involves Divisions 2 to 14 of the Facilities Construction Subgroup. Although the basis for sequencing the Divisions in this subgroup is far more complicated, the first few divisions (those that are used in virtually all buildings) may be deduced by visualizing the sequence of postearthwork operations required in constructing the simple building shown in  Figure 1.5   . The building consists of load-bearing masonry walls, steel roof joists, and wood roof deck.

  FIGURE 1.5 A simple load-bearing masonry wall building with steel roof trusses and wood roof
deck used as an aid to recalling the sequence of the first few (architecturally important) divisions of
the MasterFormat.

The first operation is the foundations for the walls. Because foundations are typically  made of concrete,   Concrete  is Division 03. After the foundations have been completed, masonry work for the walls can begin. Thus,   Masonry  is Division 04. After the walls are completed, steel roof joists can be placed. Thus, Division 05 is   Metals . The installation of the wood roof deck follows that of the steel joists. Hence,   Wood, Plastics, and Composites is Division 06.

After the roof deck is erected, it must be insulated and protected against weather. Therefore,   Thermal and Moisture Protection  is Division 07. Roofing and waterproofing (of basements) are part of this division, as are wall insulation and joint sealants. The next step is to protect the rest of the envelope; hence, Division 08 is   Openings . All doors and windows are part of this division, regardless of whether they are made of steel, aluminum, or wood.

With the envelope protected, finish operations, such as those involving the interior dry-wall, flooring, and ceiling, can begin. Thus, Division 09 is   Finishes . Division 10 is   Special-
ties , which consists of several items that cannot be included in the previous divisions, such
as toilet partitions, lockers, storage shelving, and movable partitions.

Obviously, the building must now receive all the necessary office, kitchen, laboratory, or other equipment. Thus, Division 11 is   Equipment . Division 12 is   Furnishings ,  followed  by  Special Construction  (Division 13) and   Conveying Equipment   (Division  14).   

Before any construction operation can begin, there must be references to items that  apply to all divisions, such as payment procedures, product-substitution procedures, contract-modification procedures, contractor’s temporary facilities, and regulatory requirements imposed by the city or any other authority having jurisdiction. This is Division 01, General Requirements  . Division 00 (  Procurement and Contracting  Requirements  ) refers to the requirements for the procurement of bids from prospective contractors.

THE CONSTRUCTION DOCUMENT SET

Just as the construction drawings are prepared separately by the architect and each consultant for their respective portions of the work, so are the specifications. The specifications from various design team members are assembled by the architect in a single document called the   project manual . Because the specifications consist of printed (typed) pages (not graphic images), a project manual is a bound document—like a book.

The major component of a project manual is the specifications. However, the project manual also contains other items, as explained later in this chapter.

The set of construction drawings (from various design team members) and the project manual together constitute what is known as the   construction document set, Figure 1.3. The construction document set is the document that the owner and architect use to invite bids from prospective contractors.

FIGURE 1.3 A construction document set consists of a set of architectural and consultants’ construction drawings plus the project manual. The project manual is bound in a book format. 

CONSTRUCTION SPECIFICATIONS

Buildings cannot be constructed from drawings alone, because there is a great deal of information that cannot be included in the drawings. For instance, the drawings will give the locations of columns, their dimensions, and the material used (such as reinforced concrete), but the quality of materials, their properties (the strength of concrete, for example), and the test methods required to confirm compliance cannot be furnished on the drawings. This information is included in the document called   specifications. 

Specifications are written technical descriptions of the design intent, whereas the drawings provide the graphic description. The two components of the construction documents—the specifications and the construction drawings—complement each other and generally deal with different aspects of the project. Because they are complementary, they  are supposed to be used in conjunction with each other. There is no order of precedence between the construction drawings and the specifications. Thus, if an item is described in  only one place—either the specification or the drawings—it is part of the project, as if  described in the other.

For instance, if the construction drawings do not show the door hardware (hinges, locks, handles, and other components) but the hardware is described in the specifications, the owner will get the doors with the stated hardware. If the drawings had precedence over the specifications, the owner would receive doors without hinges and handles.

Generally, there is little overlap between the drawings and the specifications. More importantly, there should be no conflict between them. If a conflict between the two documents is identified, the contractor must bring it to the attention of the architect promptly. In fact, construction contracts generally require that before starting any portion of the project, the contractor must carefully study and compare the drawings and the specifications and report inconsistencies to the architect.

If the conflict between the specifications and the construction drawings goes unnoticed initially but later results in a dispute, the courts have in most cases resolved it in favor of the specifications—implying that the specifications, not the drawings, govern the project. However, if the owner or the design team wishes to reverse the order, it may be so stated in the owner-contractor agreement.

CONSTRUCTION DRAWINGS

During the CD stage, the architect and consultants prepare their own sets of drawings, referred to as   construction drawings . Thus, a project has architectural construction drawings, civil and structural construction drawings, MEPF construction drawings, landscape construction drawings, and so on.

Construction drawings are dimensioned drawings (usually computer generated) that  fully delineate the building. They consist of floor plans, elevations, sections, schedules, and  various large-scale details. The details depict a small portion of the building that cannot be  adequately described on smaller-scale plans, elevations, or sections.    

Construction drawings are the drawings that the construction team uses to build the  building. Therefore, they must indicate the geometry, layout, dimensions, types of materials, details of assembling the components, colors and textures, and so on. Construction drawings are generally two-dimensional drawings, but three dimensional isometrics are sometimes used for complex details. Construction drawings are also used by the contractor to prepare a detailed cost estimate of the project at the time of bidding.

Construction drawings are not a sequence of assembly instructions, such as for a bicycle. Instead, they indicate what every component is and where it will be located when the building is completed. In other words, the design team decides the “what” and “where” of the building. The “how” and “when” of the building are entirely in the contractor’s domain.

NOTE

Working Drawings and Construction Drawings The term working drawings was used until the end of the  twentieth century for what are now commonly referred to as construction drawings.

BUILDING DESIGN DEVELOPMENT (DD) STAGE—EMPHASIS ON DECISION MAKING

Once the schematic design is approved by the owner, the process of designing the building in greater detail begins. During this stage, the schematic design is developed further—hence the term   design development  (DD) stage.

While the emphasis in the SD stage is on the creative, conceptual, and innovative aspects of design, the DD stage focuses on developing practical and pragmatic solutions for the  exterior envelope, structure, fenestration, interior systems, MEPF systems, and so forth.

This development involves strategic consultations with all members of the design team. Therefore, the most critical feature of the DD stage is decision making, which may range  from broad design aspects to details. At this stage, the vast majority of decisions about  products, materials, and equipment are made. Efficient execution of the construction documents depends directly on how well the DD is managed. A more detailed version of the specifications and probable cost of the project is also prepared at this stage.  

BUILDING SCHEMATIC DESIGN (SD) STAGE—EMPHASIS ON DESIGN

The schematic design gives graphic shape to the project program. It is an overall design concept that illustrates the key ideas of the design solution. The major player in this stage is the architect, who develops the design scheme (or several design options) with only limited help from the consultants. Because most projects have strict budgetary limitations, a rough estimate of the project’s probable cost is generally produced at this stage.

The schematic design usually goes through several revisions, because the first design scheme prepared by the architect will rarely be approved by the owner. The architect communicates the design proposal(s) to the owner through various types of drawings—plans, elevations, sections, freehand sketches, and three dimensional graphics (isometrics, axonometrics, and perspectives). For some projects, a three-dimensional scale model of the entire  building or the complex of buildings, showing the context (neighboring buildings) within which the project is sited, may be needed.

With significant developments in electronic media technology, especially building information modeling (BIM), computer-generated imagery has become common in architecture and related engineering disciplines. Computer-generated walk-through and flyover simulations are becoming increasingly popular ways of communicating the architect’s  design intent to the owner and the related organizations at the SD stage.

It is important to note that the schematic design drawings, images, models, and simulations, regardless of how well they are produced, are not adequate to construct the building. Their objective is merely to communicate the design scheme to the owner (and to consultants, who may or may not be on board at this stage), not to the contractor.

BUILDING DESIGN PHASE

The    design phase   begins after the selection of the architect. Because the architect (usually a firm) may have limited capabilities for handling the broad range of building-design activities, several different, more specialized consultants are usually required, depending on the size and scope of the project.

In most projects, the design team consists of the architect, civil and structural consultants, and mechanical, electrical, plumbing, and fire-protection (MEPF) consultants. In complex projects, the design team may also include an acoustical consultant, roofing and waterproofing consultant, cost consultant, building code consultant, signage consultant, interior designer, landscape architect, and so on.

Some design firms have an entire design team (architects and specialized consultants) on staff, in which case the owner will contract with a single firm. Generally, however, the design team comprises several different design firms. In such cases, the owner typically contracts the architect, who in turn contracts the remaining design team members,  Figure 1.1. Thus, the architect functions as the prime design professional and, to a limited degree, as the owner’s representative. The architect is liable to the owner for his or her own work and that of the consultants. For that reason, most architects ensure that their consultants carry adequate liability insurance.

  FIGURE 1.1 Members of a typical design team, and their interrelationships with each other and
the owner in a traditional contractual setup. A line in this illustration indicates a contractual rela-
tionship between parties. (“MEPF consultants” is an acronym for mechanical, electrical, plumbing
and fire consultants.)    
In some projects, the owner may contract some consultants directly, particularly a civil consultant (for a survey of the site, site grading, slope stabilization, and site drainage), a geotechnical consultant (for investigation of the soil properties), and a landscape architect (for landscape and site design),  Figure 1.2   . These consultants may be engaged before or at the same time as the architect.  

  FIGURE 1.2 Members of a typical design team, and their interrelationships with each other and
the owner in a project where some consultants are contracted directly by the owner. A solid line
in this illustration indicates a contractual   relationship between parties. A dashed line indicates a
communication link, not a contract.    

Even when a consultant is contracted directly by the owner, the architect retains some liability for the consultant’s work. This liability occurs because the architect, being the prime design professional, coordinates the entire design effort, and the consultants’ work is influenced a great deal by the architectural decisions. Therefore, the working relationship between the architect and an owner-contracted consultant remains essentially the same as if  the consultant were chosen by the architect.

In some cases, an engineer or another professional may coordinate the design process.

This  generally occurs when a building is a minor component of a large-scale project. For example, in a  highly  technical project such as a power plant, an electrical engineer may be  the prime design professional.

In most building projects, the design phase consists of three stages:

  •     Schematic  design   stage
  •     Design  development   stage
  •     Construction  documents   stage

(BUILDING) PROJECT PREDESIGN PHASE

During the   predesign phase  (also called the   planning phase  ), the project is defined in terms of its function, purpose, scope, size, and economics. This is the most crucial of the five phases, and is almost always managed by the owner and the owner’s team. The success or failure of the project may depend on how well this phase is defined, detailed, and managed. Obviously, the clearer the project’s definition, the easier it is to proceed to the subsequent phases.

Some of the important predesign tasks are:

•    Building program definition
•    Economic feasibility assessment,  including the project’s overall budget and financing
•    Site assessment and selection,  including verifying the site’s appropriateness and determining its designated land use
•    Governmental constraints assessment,   for example, building code and zoning constraints and other legal aspects of the project
•    Sustainability rating —whether the owner would like the project to achieve the U.S. Green Building Council’s (USGBC’s) Leadership in Energy and Environmental Design (LEED) certification at some level
•    Design team selection

BUILDING (PROJECT) PROGRAM 

This includes defining the activities, functions, and spaces required in the building, along with their approximate sizes and their relationships with each other. For a house or another small project, the programis usually simple and can be developed by the owner without external assistance. For a large project, however,where the owner may be an institution (such as a corporation, school board, hospital, religious organization, or governmental entity), developing the program may be a complex exercise. This may be due to the size and complexity of the project or the need to involve several individuals—a corporation’s board  of directors, for example—in decision making. These constituencies may have different views of the project, making it difficult to create a consensus.

Program development may also be complicated by situations in which the owner has a fuzzy idea of the project and is unable to define it clearly. By contrast, experienced owners tend to have a clear understanding of the project and generally provide a detailed, unambiguous program to the architect.

It is not unusual for the owner to involve the architect and a few other consultants of the design team in preparing the program. In this instance, the design team may be hired during the predesign phase. When the economic considerations of the project are paramount, the owner may also consult a construction cost analyst.

Whatever the situation, preparing the program is the first step in the project delivery process. It should be spelled out in writing and in sufficient detail to guide the design, reduce the liability risk for the architect, and avoid its misinterpretation. If a revision is made during the progress of the project, the owner’s written approval is necessary.

BUILDING PROJECT DELIVERY PHASES

The process by which a building project is delivered to its owner may be divided into the following five phases, referred to as the   project delivery phases . Although there is usually some overlap between adjacent phases, they generally follow this order:

  •     Predesign  phase
  •     Design  phase
  •     Preconstruction  phase
  •     Construction  phase
  •     Postconstruction  phase

FOR PRELIMINARY DESIGN OF A WOOD LIGHT FRAME STRUCTURE

Estimate the depth of wood rafters on the basis of the horizontal (not slope) distance from the outside wall of the building to the ridge board in a gable or hip roof and the horizontal distance between supports in a shed roof. A 2 X 4 rafter spans approximately 7 feet (2.1 m), a 2 X 6 10 feet (3.0 m), a 2 8 14 feet (4.3 m), and a 2 X 10 17 feet (5.2 m).

The depth of wood light roof trusses is usually based on the desired roof pitch. A typical depth is one-quarter of the width of the building, which corresponds to a 6/ 12 pitch in a gable truss. Trusses are generally spaced 24 inches (600 mm) o.c. and can span up to approximately  65 feet (20 m).

Estimate the depth of wood floor joists as follows: 2 x 6 joists span up to 9 feet (2.7 m), 2 x 8 joists 11 feet (3.4 m), 2 x 10 joists 14 feet (4.3 m), and 2 x 12 joists 17 feet (5.2 m).

Estimate the depth of manufactured  wood I-joists as follows: 9½-inch (240-mm) joists span 16 feet (4.9
m), 117 /8 -inch (300-mm) joists 19 feet (5.8 m), 14-inch (360-mm) joists span 23 feet (7.0 m), and 16-inch (400-mm) joists span 25 feet (7.6 m).

Estimate the depth of  wood floor  trusses as 1/ 18 of their span. Typical depths of ß oor trusses range from 12 to 28 inches (305-710 mm) in 2-inch (51-mm) increments.

2 X 4 wood studs 24 inches (600 mm) o.c. can support attic and roof loads only. Either 2 X 4 studs 16 inches (400 mm) o.c. or 2 6 studs 24 inches o.c. can support one floor plus attic and roof. 2 X 6 studs 16 inches o.c. can support two ß oors plus attic and roof.

Framing members in light frame buildings are usually spaced either 16 or 24 inches (400 or 600 mm) o.c. For actual sizes of dimension lumber in both conventional and metric units, see Figure 3.22.

These approximations are valid only for purposes of preliminary building layout and must not be used  to select final member sizes. They apply to the normal range of building occupancies such as residential, office, commercial, and institutional buildings. For manufacturing and storage buildings, use somewhat larger  members.

Figure 3.22 The relationship between nominal and
actual dimensions for the most common
sizes of kiln-dried lumber is given in this
simplified chart

Prefabricated Framing Assemblies

Roof trusses, and to a lesser extent floor trusses, are used in platform frame buildings because of their speed of erection, economy of material usage, and long spans. Though many floor  trusses are light enough to be lifted and installed by two carpenters, most truss assemblies are erected with the  aid of a small crane that often is attached to the truck on which the trusses are delivered (Figure 5.65).  Roof trusses are particularly slender in proportion, usually only 1½ inches (38 mm) thick and capable of spanning 24 to 32 feet (7.5 to 10 m). They must be temporarily braced during construction to prevent buckling or  the dominolike collapse of all the trusses until they are adequately secured permanently by the application of roof sheathing panels and interior finishes (Figure 5.66).

Figure 5.65 Roof trusses are typically lifted to the roof by a  boom mounted on the delivery truck. This is one  of a series of identical attic trusses, which will  frame a habitable space under the roof.
Figure 5.65
Roof trusses are typically lifted to the roof by a
boom mounted on the delivery truck. This is one
of a series of identical attic trusses, which will
frame a habitable space under the roof.

Manufactured wall panels have been adopted more slowly than roof and floor trusses, and are used mostly  by large builders who build hundreds or thousands of houses per year. For  the smaller builder, wall framing can be done on site with the same amount of material as with panels and with  little or no additional overall expenditure of labor, especially when the building requires walls of varying heights and shapes.

Figure 5.66 A roof framed with prefabricated
trusses. Approximately midway up the
upper chords of the trusses, temporary
strapping ties the trusses to one another
for bracing. Other diagonal bracing, not
visible in this photograph, ties the trusses
to floor or ceiling framing to prevent
the entire row from collectively tipping
sideways.

Construction: Framing for Optimal Lumber Usage

In wood light frame structures constructed with  advanced framing techniques (also called optimum value engineering), special attention is given to minimizing the use of redundant or structurally unnecessary wood members, thereby reducing the amount of lumber required to construct the frame and, once the frame is insulated, increasing its thermal efficiency (Figure 5.64). A variety of techniques may be used, including:

Spacing framing members at 24 inches (610 mm) rather than 16 inches (406 mm) o.c.: Wider spacing of framing members reduces the amount of lumber required. In exterior walls,  thermal efficiency is also improved by the reduction in thermal bridging area in comparison to walls framed with more closely spaced members.

Designing to a 24-inch (610-mm) module: When the outside dimensions of a framed structure conform  to a 24-inch module, sheathing panel waste is minimized. Planning rough opening sizes and locations in floors,  walls, and roofs to conform, where possible, to modular dimensions can  reduce waste even further.

Designing to modular dimensions also reduces wastage of interior wallboard.

Using single top plates in all walls, both bearing and nonbearing: In the  case of bearing walls, this requires  floor or roof framing members to align directly over studs in the walls  that support them.

Figure 5.64 Comparison of walls framed with  conventional and advanced techniques.
Wall A is framed . Studs are spaced at
16 inches (406 mm) o.c., the layout  of the wall and its openings is not
coordinated with the framing module,  and standard details are used for
corners, openings, and other features.  In wall B, studs are spaced at 24 inches
(610 mm) o.c., the length of the wall and
the location and size of its openings have  been coordinated to the greatest extent
possible with the 24-inch module, and redundant framing members have been
eliminated. Note that with the single top plate, fl>oor joists or roof rafters (shown
dashed in these figures) bearing on wall B must fall directly over studs below. The
total length of framing lumber used in  wall B is half of that required for wall A.
Though only a foot and a half shorter in  length, wall B also can be sheathed with five standard-sized sheathing panels,
whereas wall A requires six. Even if  wall A is constructed of 2 X 4 studs and
wall B is constructed of 2 X 6 studs, the  overall savings in materials and reduction
in waste in wall B are substantial.

Minimizing  other  unneeded framing members: Don't use headers over openings in nonbearing walls,  since they are not needed; in bearing walls, use headers only as deep as  required for the loads and span.  Where corner studs serve only to provide nailing surfaces or support  for wallboard, use other, less waste- ful blocking techniques or metal clips  designed for this purpose instead. Replace jack studs supporting headers at window and door openings with metal hangers; eliminate unneeded cripple studs under rough  sills. All of these techniques save lumber and, in exterior walls, increase energy efficiency by reducing thermal bridging through solid framing members.

Eliminating unneeded plywood and OSB wall sheathing: Where let-in bracing is structurally adequate  for lateral force resistance, eliminate structural panel wall sheathing entirely and cover walls with insulating  sheathing for better thermal efficiency. Where structural panels are required, use the minimum extent of  panels necessary.

Advanced framing techniques rely on unconventional framing methods and significantly  reduce  redundancy in the building frame. For these reasons, they should not  be used without guidance from a  structural engineer or other qualified design professional, and special review and approval from local building authorities may be required. Nevertheless, where these techniques  are used, significant benefits can be realized. According to the National Association of Home Builders Partnership for Advancing Technology in Housing, advanced framing techniques can reduce the amount of  lumber used in a wood light frame  structure by up to 19 percent and  improve the energy efficiency of the insulated structure by as much as 30 percent.

Construction: Framing for Increased Thermal Efficiency

The 2 x 4 (38 x 89 mm) has been the standard-size wall stud since light framing was invented. In recent  years, however, pressures for heating fuel conservation have led to energy code requirements for more thermal insulation than can be inserted in the cavities of a wall framed with  members only 3½ inches (89 mm) deep. One solution is to frame walls with 2 x  6 (38 x 140 mm) studs, usually at a spacing of 24 inches (610 mm), creating an insulation cavity 5½ inches (140 mm) deep. Alternatively,  2 x 4-framed walls may be covered either inside or out with insulating plastic foam sheathing, thus reaching an insulation value about the  same as that of a conventionally insulated 2   6-framed wall. For even greater insulation performance, 2   6 studs and insulating sheathing may be used in tandem. Alternatively, in very cold climates, even deeper wall  assemblies that can achieve greater insulation values may be constructed of two separate layers of wall studs  or of vertical truss studs made up of pairs of ordinary studs joined at intervals by plywood plates. Some of these constructions methods are illustrated in Figures 7.17 through 7.21.

Figure 7.17
Insulation levels in walls of light frame buildings can be increased from the R13 to R-15 (RSI-90 to RSI-104) of a
2 x 4 stud wall to R19 (RSI-132) or more by using either 2 x 6 framing and thicker batt insulation (left) or 2 x 4
framing with plastic foam sheathing in combination with batt insulation (right). The foam sheathing insulates the
wood framing members as well as the cavities between them but can complicate the process of installing some types
of siding.
Figure 7.18
Window and door headers in 2 x 6 framing require special
detailing. Two alternative header details are shown here in
section view: (a) The header members are installed flush
with the interior and exterior surfaces of the studs, with an
insulated space between. This detail is thermally efficient
but may not provide sufficient nailing for interior finish
materials around the window. (b) A 3 x 2 spacer provides
full nailing around the opening.
Figure 7.19
Two alternative corner post details for 2 x 6 stud walls, shown in plan view: (a) Each wall frame ends with a full 2 x 6 stud, and a 2 x 4 nailer is added to accept fasteners from the interior wall finish. (b) For maximum thermal efficiency, one wall frame ends with a 2 x 4 stud flush with the interior surface, which eliminates any thermal bridging through studs.
Figure 7.20
With the two framing methods shown here, walls can be insulated to any desired
level of thermal resistance.
Figure 7.21
A raised-heel roof truss provides plenty
of space for attic insulation at the eave.

Roof Framing

The generic roof shapes for wood light frame buildings are shown in Figure 5.50. These are often combined to make roofs that are suited to the covering of more complex plan shapes and building volumes.

Figure 5.50 Basic roof shapes for wood light frame
buildings.




For structural stability, the rafters in gable and hip roofs must be securely tied together at the top of the supporting walls by well-nailed ceiling joists to make what is, in effect, a series of tri- angular trusses. If the designer wishes to eliminate the ceiling joists to expose  the sloping underside of the roof as  the finished ceiling surface, a beam or bearing wall must be inserted at the  ridge or a system of exposed horizontal  ties must be used in place of the ceiling joists. Sometimes a designer wishes  to raise the ceiling joists or exposed ties to a higher elevation than the tops of the wall plates. This greatly increases  the bending forces in the rafters and should be done only after consultation with a structural engineer.

Although a college graduate  ar  chitect or engineer would find it difficult  to lay out all the cuts of the rafters for a sloping roof using trigonometry, a  skilled carpenter, without resorting to  mathematics, has little problem making the layout if the  pitch (slope) is  specified as a ratio of rise to run. Rise is  the vertical dimension and run is the  horizontal. In the United States, pitch  is usually given on the architectÕs drawings as inches of rise per foot (12 inches) of run. A skilled carpenter uses  these two figures on the two edges of  a framing square to lay out the rafter as  shown in Figures 5.52 and 5.58. The  actual length of the rafter is never figured, nor does it need to be, because all the measurements are made as  horizontal and vertical distances with  the aid of the square. Today, many  carpenters prefer to do rafter layout  with the aid of tables that give actual  rafter lengths for various pitches and  horizontal distances; these tables are  stamped on the framing square itself  or printed in pocket-size booklets. Also available are hand-held calcula- tors that are specially programmed to find dimensions of rafters.

Hips and valleys introduce another level of trigonometric complexity  in rafter layout, but the experienced  carpenter has little difficulty  even  here: Again, he or she can use published tables for hip and valley rafters or do the layout the traditional way, as illustrated in Figure 5.56. The  head carpenter lays out only one rafter of each type by these procedures. This then becomes the  pattern rafter from which other carpenters trace  and cut the remainder of the rafters (Figure 5.59).

In areas that are subject to hurricanes, the building codes may require  that rafters be attached to their sup- porting walls with sheet metal rafter anchors. The type, size, and spacing of the nails that attach the roof sheathing to the rafters are also closely controlled.  The intent of both of these measures is to reduce the likelihood that the roof  will be blown off in high winds. Similar to requirements for bridging in floor joists, the International  Residential Code requires bridging  for ceiling joists and rafters where the  depth of these members exceeds their  thickness by a ratio of 6 to 1 based on   nominal dimensions (for conventional solid wood framing, members deeper  than 2 12 or 38 286 mm). Where  the undersides of the joists or rafters  remain unfinished, wood strapping  nailed perpendicular to the bottoms of the joists or rafters may be used instead of solid blocking or crossbracing installed between framing members.

Figure 5.52
Roof framing details and procedures: The lettered details are keyed to Figure 5.53.
The remainder of the page shows how a framing square is used to lay out a pattern rafter,
reading from the fi rst step at the lower end of the rafter to the last step at the top.
  

Figure 5.53
Step Seven: framing the attic fl oor and roof. The outer ends of attic
fl oor joists are not usually headed off, but instead are face nailed to
the rafter pairs that overlap them.
Figure 5.54
A summary of the major details for the structure shown in
Figure 5.55, aligned in relationship to one another. The gable
end studs are cut as shown in A and face nailed to the end rafter.
Figure 5.55
Step Eight: The sheathed frame is completed. The letters A,
B, and C indicate portions of the framing that are detailed in
Figure 5.54.
Figure 5.56
Framing for a hip roof. The diffi  cult
geometric problem of laying out the
diagonal hip rafter is solved easily by
using the framing square in the manner
shown. Toward the bottom of the rafter
shown in the lower part of this fi  gure
is a birdsmouth cut, an angled notch in
the rafter that allows the rafter to seat
securely on the top plate of the wall.

Figure 5.57
Framing for an overhanging rake.

Figure 5.58
A framing square being used to mark
rafter cuts. The run of the roof,
12 inches, is aligned with the edge of the
rafter on the blade (the wider leg) of a
square, and the rise, 7 inches in this case,
is aligned on the tongue (the narrower
leg) of the square. A pencil line along
the tongue will be perfectly vertical (a
plumb cut) when the rafter is installed in
the roof, and one along the blade will be
horizontal (a level cut). True horizontal
and vertical distances can be measured
on the blade and tongue, respectively.
The layout of these types of cuts can also
be seen in Figures 5.52 and 5.56.

Figure 5.59
Tracing a pattern rafter to mark cuts for
the rest of the rafters. The corner of
the building behind the carpenters has
let-in corner braces on both fl oors, and
most of the rafters are already installed.

WALL FRAMING, SHEATHING, AND BRACING

Wall framing, like floor framing, is laid out in such a way that a framing member, in this case a stud, occurs under each vertical joint between sheathing panels (Figures 5.29-5.32). The  lead carpenter initiates wall framing by laying out the stud locations on the  top plate and sole plate of each wall. Other carpenters follow behind to cut the studs and headers and assemble the walls in a horizontal position  on the subfloor. As each wall frame is completed, it is tilted up and nailed into position, with temporary bracing  as needed (Figures 5.34-5.37).

Figure 5.29 Typical ground-floor
wall framing details,
keyed by letter to
Figure 5.30.


Figure 5.30 Step Four in erecting a platform frame building:
The ground-floor walls are framed. The letters A,
B, and C indicate portions of the framing that are
detailed in Figure 5.29.
Figure 5.31 Framing details for nonloadbearing interior
partitions.

Figure 5.32
Steps in the framing of a typical wall and details at wall intersections and a
window opening. In D, the short studs above the header and below the rough
sill are called trimmer or cripple studs.
Figure 5.33 As the fi rst step in constructing a wall
frame, the chief carpenter aligns the
top plate and sole plate side by side on
the floor platform and marks each stud
location on both of them simultaneously
with a pencil and framing square.



Figure 5.34 Nailing studs to a plate, using a pneu-
matic nail gun. The triple studs are for
a partition intersection.
Figure 5.35
Tilting an interior partition into position.
The gap in the upper top plate will
receive the projecting end of the upper
top plate from another partition that
intersects at this point.


Figure 5.36
Fastening a wall to the floor platform.
Horizontal blocking between studs as
seen toward the left in this photo is
typically installed to provide a solid
substrate for the later attachment of
bathroom hardware, exterior panels,
or any number of possible other items.

Figure 5.37
Lower-level wall framing is held up by
temporary diagonal bracing until the floor joist framing is in place above and
wall bracing or sheathing is complete,
after which the frame becomes
completely self-bracing. The outer
walls of this building are framed with
2 x 6 (38 x 140 mm) studs to allow for a
greater thickness of thermal insulation,
whereas the interior partitions are made
of 2 x 4 (38 x 89 mm) stock.

Figure 5.38
Prefabricated shear wall panels are
especially useful in garage wall framing
or other walls with large openings where
only narrow, solid sections of wall
remain to resist lateral forces. They may
be made of all wood components or,
where even greater strength is required,
of wood and metal, as shown here.
The corrugated galvanized steel in this
panel is over 1/ 8  inch (3.5 mm) thick,
and the panel’s capacity to resist lateral
forces is several times greater than that
of comparable all-wood prefabricated
panels. The bottom of the panel will be
anchored with bolts embedded 21 inches
(533 mm) or more into the concrete
foundation, and the sides and top will
be screw-fastened to the surrounding
wood framing. Holes in the panel can
accommodate wiring runs within the
wall.


Long studs for tall walls often must be larger than a 2 X 4 in order  to resist wind forces. Because long  pieces of sawn dimension lumber tend not to be straight and may be less  readily available, studs manufactured  of structural composite lumber may  be used instead. The International Residential Code requires horizontal  wood blocking to be installed between studs at midheight in wall frames that are taller than 10 feet (3 m). The purpose of this blocking is to stop off the cavities between studs to restrict the  spread of fire.

Headers over window and door openings must be sized in accordance  with building code criteria. Typically,  a wall opening header consists of two nominal 2-inch members standing on  edge, separated by a plywood spacer  that serves to make the header as  thick as the depth of the wall studs.  Headers for long spans and/or heavy loads are often made of laminated  veneer lumber or parallel strand lumber, either of which is stronger and stiffer than dimension lumber. Several manufacturers market prefabri- cated headers that include thermal insulation as a way of reducing the heat loss that occurs through these difficult-to-insulate assemblies. At either end, headers rest on shortened studs called trimmer or jack studs, which  themselves are nailed to full-height king studs. At the bottom of a window  opening, the  rough sill is supported  on cripple studs (Figure 5.32).

Each corner and partition intersection must furnish nailing surfaces for the edge of each plane of exterior  and interior finish materials. This requires a minimum of three studs  at each intersection, unless special  metal clips are used to reduce the number to two (Figure 5.32).

Sheathing was originally made of solid boards, usually 6 to 10 inches  (150 to 250 mm) wide. If applied  horizontally, these boards did little  to brace the building against wracking caused by the forces of wind or
earthquake. If applied on a diagonal, however, they produced a rigid frame. Today, walls are sheathed with  either plywood or OSB, which provide permanent, very stiff bracing, or with let-in bracing  as described below. Panels are applied as soon as possible after the wall  is framed, often while it is still lying on the floor platform.

In regions of strong winds or earthquakes, wall sheathing plays  a very important part in the lateral stability the structure. A properly sheathed wall acts as a  shear wall to  resist lateral forces. Both interior and  exterior walls can act as shear walls,  which must be provided in both east west and north-south orientations  and must be distributed more or less symmetrically in the floor plan. Stresses within shear walls are proportional  to their length, with shorter walls being subjected to higher stresses than those that are longer. Where walls have large openings for windows or doors, the remaining solid portions  that can contribute to lateral force resistance may become relatively short and therefore exposed to very  high stresses. In such cases, sheathing may have to be attached with  larger nails at very close spacings, the  horizontal edges of sheathing panels  may have to be supported by wood  blocking to keep them from buckling, and studs over which sheathing panels join may need to be larger in  size, such as 3 x or 4 x (64 mm or 89 mm) members, in order to hold  the required nails without splitting.

Where the needed strength cannot  be reliably achieved using site-con- struction methods, factory-fabricated  panels made of wood or steel com- ponents may be used (Figure 5.38).  Shear walls subject to high forces may also require hold-downs to prevent the  walls from pulling up off the foundation or floor platform (Figures 5.39-5.41). Consultation with a structural engineer is recommended (and often  legally required) when building in areas that are earthquake-prone or subject to very high wind forces.

Sheathing panels made from wood or paper fiber, plastic foam, and glass fiber are intended principally as  thermal insulation and to provide a base for water-resistant building paper or house wrap. Most panels of these types are nonstructural, so walls sheathed with such panels rely on  letin diagonal bracing or strategically located structural panels for lateral force  resistance. Let-in bracing may be made  of wood members, such as 1 x 4 (19 x 89 mm) boards, or light steel members that are recessed into the outer  face of the studs of the wall before it is sheathed (Figures 5.32 and 5.42).

Figure 5.39
Strap tie hold-downs are made of galvanized steel straps with hooked
or deformed ends cast into the concrete foundation wall (top). After
the wall is framed, the exposed length of strap may be nailed directly
to framing or, as seen here, nailed through the sheathing into the studs
or posts behind (bottom). The number, size, and spacing of nails used
to fasten the strap depend on the magnitude of the loads that must be
resisted and the capacity of the wood member to hold nails without
splitting. In the top image, anchor bolts cast into the top of the foun-
dation wall that will be used to secure the sill plate in place are also
visible.

Figure 5.40
Hold-downs made from threaded rod and steel plate
anchors can resist much greater forces than strap tie
hold-downs. They may be used at each floor level to
securely tie the full height of the building frame to its
foundation. For the type shown here, the nuts at the
ends of the threaded rods may require retightening
after the fi rst heating season to compensate for wood
shrinkage, which can mean that access holes must be
provided through the interior wall surfaces. Other
models rely on spring-loaded tapered shims or other
mechanical compensation so as to be self-adjusting
Figure 5.41
A heavy-duty seismic hold-down similar to that illustrated in Figure 5.40. The anchor
rod with one end cast into the concrete foundation wall protrudes through the
preservative-treated wood sill where its threaded end is bolted to the anchor. The
anchor in turn is bolted to a 4 4 (89 89 mm) post with fi ve bolts of substantial
diameter. A conventional foundation anchor bolt with an oversized square washer is
also partially visible to the right of the hold-down. Also note the thicker-than-normal,
3-inch nominal (64-mm) sill plate, a common feature in wood light framing designed
for high seismic forces.
Figure 5.42
Applying a panel of insulating foam sheathing. Because this
type of sheathing is too soft and weak to brace the frame,
diagonal bracing is inserted into the outside faces of the
studs at the corners of the building. Steel bracing, nailed at
each stud, is used in this frame and is visible just to the right
of the carpenter’s leg.